Garland, TX SWPPP & Stormwater Requirements

Updated August 2026
Garland wants its paperwork before the dirt and its inspections on a compound clock — the city's code sets both in writing.
What does Garland require for SWPPP compliance?
Any operator seeking coverage for stormwater discharges from a construction site under the TPDES construction general permit must submit a signed copy of the notice of intent — or, for one-to-five-acre projects, the site notice — to the City of Garland at least two days prior to the commencement of construction activities. File it with mobilization.
The city meets you two days early — miss the window and the schedule slips before the first bucket turns, so the submittal belongs in the mobilization plan, not the punch list.
The compound inspection clock
Once work runs, the cadence is written into the city code. Garland's stormwater code requires qualified personnel to inspect disturbed areas, exposed material storage, structural control measures, and vehicle entry and exit points at least once every seven calendar days and within 24 hours of the end of a storm that is 0.5 inches or greater. Weekly and rain-triggered — both clocks run at once, and the record has to show it.
The state permit still applies
The city's rules sit on top of the state's, not in place of them. A stormwater pollution prevention plan (SWP3) must be prepared and implemented before construction activities begin. TXR150000's standard schedule requires construction site inspections at least once every 14 calendar days and within 24 hours of the end of a storm event of 0.5 inches or greater. The city's layer gets the project reviewed; the state permit's obligations run for the life of the disturbance.
Inspections and the record
The operator owns the inspection record from first disturbance to final stabilization. Terradyne provides routine SWPPP inspection reports with cloud-based client access. See SWPPP Inspections for how the program works, and Silt Fence Installation for the perimeter the reviewers will look at first.
Check before you mobilize
Ordinances and city standards get revised; confirm the current documents with the city before you mobilize. For other North Texas cities, start at Local Compliance.
Frequently Asked Questions
What does Garland need before construction starts?
A signed copy of the state coverage paperwork — the notice of intent, or the site notice for one-to-five-acre projects — submitted to the city at least two days before construction begins.
How often does Garland expect construction inspections?
On the city's own written cadence — a weekly clock and a rain-triggered one running at the same time, with the record expected to show both.
Does the state permit still apply inside Garland?
Yes — the city's submittal and inspection requirements ride on top of the state program, whose obligations run from the first disturbance to final stabilization.